GRANITE LEAD TIME & SCHEDULING

How should engineering granite lead time be confirmed?

Direct answer: Granite lead time cannot be calculated from area or machine count alone. A workable schedule must confirm drawings, samples, material batches, size mix, quantity, processes, inspection and corrective work, packing and destination, then place six milestones—technical freeze, material, production, acceptance, packing and dispatch—in the written order.

Updated 2 September 2026 · Capacity figures supplied by Shandong Kaizhong Stone Co., Ltd.; each project requires a written schedule

Information required before scheduling

InputConfirmSchedule effect
Product and drawingsGranite, product type, current CAD/PDF and part IDsDefines material, machinery, processes and trial fit
Sizes and quantitiesLength, width, thickness, size mix, holes, slots and custom detailsDefines cutting plan, process time and inspection workload
Sample and finishColour range, flamed/bush-hammered/polished/honed finish and edgesDefines approval and surface-processing stages
Quality and releaseTolerance, sampling, dry lay, third-party inspection and witness pointsDefines inspection, corrective action and release time
Packing and transportPallet/crate, piece and case weight, port or project destinationDefines packing, loading, documents and logistics
Required dateRequested ex-works, shipment or arrival date and split-delivery needUsed for backward planning; not an automatic factory commitment

Six delivery milestones to place in the order

  1. Technical freeze

    Approve the current drawings, cutting list, sizes, quantities, tolerances, faces and part IDs.

  2. Sample approval

    Approve granite, colour range, finish, edges and visible-face appearance.

  3. Material and batch reservation

    Verify blocks or semi-finished stock, batches, replenishment and batch-change rules.

  4. Production and in-process inspection

    Schedule each process and record first article, dimensions, finish and exceptions.

  5. Final inspection and packing

    Complete sorting or dry lay, final checks, case numbers, labels and packing photographs.

  6. Dispatch and arrival coordination

    Confirm loading, documents, destination, unloading conditions and estimated arrival milestone.

Six common causes of schedule delay

01 / RISK

Drawing changes

Changing sizes, quantities, holes or slots after scheduling affects material use, processing and inspection.

02 / RISK

Complex size mix

Multiple sizes, small batches, custom pieces and trial fitting increase process changes and identification work.

03 / RISK

Late sample approval

Production lacks a stable acceptance baseline until colour and finish samples are approved.

04 / RISK

Material batch change

Replenishment or a new batch may require colour selection, a new sample or dry-lay adjustment.

05 / RISK

Inspection and rework

Third-party inspection, witness points and corrective work require scheduled time.

06 / RISK

Packing and logistics

Crate rules, weight limits, booking, trucks, ports and unloading conditions affect dispatch.

Company-reported capacity baseline

These figures help buyers understand base capability and ask scheduling questions. They do not mean capacity has been reserved for a specific order.

26Large cutting machines
15Mid-size cutting machines
11Infrared bridge saws
25–30 truckloads/dayCompany-reported routine dispatch capability
Approx. 28,000 m³/yearKerbstone capacity
Approx. 1.8–2.0M m²/yearSlab capacity

Limits of lead-time information

Machine counts and annual capacity indicate baseline fabrication capability but cannot determine one project date. Actual timing remains subject to material, drawing changes, size mix, current work, inspection and rework, packing, transport and external events.

Continue with factory capacity, the factory audit checklist and the quality inspection guide.

LEAD TIME FAQ

Questions about engineering granite lead time

Is there a standard lead time for every granite order?

No. Lead time depends on granite and batch, drawing completeness, size mix, quantity, finish, quality requirements, current production, packing and destination. A written schedule should be prepared for the specific enquiry.

How can a buyer verify that a proposed schedule is workable?

Ask the factory to connect the date to material status, relevant machinery, current work in progress, sample approval, production, inspection, packing and dispatch milestones, with responsibilities and prerequisites for each stage.

When does the lead-time clock start?

The order should define the starting condition, such as contract effectiveness, deposit, technical freeze, sample approval or material confirmation. Different starting conditions produce different dates; “after order” alone is ambiguous.

Can a large project use split deliveries?

Yes, subject to agreement. Build the plan around installation sequence, sizes, case numbers, quantity per batch and site demand, then confirm inspection, packing, transport and replenishment for each release.

Are ex-works, shipment and arrival dates the same?

No. Factory completion, loading, vessel shipment and project arrival are separate milestones. Procurement documents should state which milestone is committed and treat transport and customs uncertainty separately.