GRANITE LEAD TIME & SCHEDULING
Direct answer: Granite lead time cannot be calculated from area or machine count alone. A workable schedule must confirm drawings, samples, material batches, size mix, quantity, processes, inspection and corrective work, packing and destination, then place six milestones—technical freeze, material, production, acceptance, packing and dispatch—in the written order.
Updated 2 September 2026 · Capacity figures supplied by Shandong Kaizhong Stone Co., Ltd.; each project requires a written scheduleApprove the current drawings, cutting list, sizes, quantities, tolerances, faces and part IDs.
Approve granite, colour range, finish, edges and visible-face appearance.
Verify blocks or semi-finished stock, batches, replenishment and batch-change rules.
Schedule each process and record first article, dimensions, finish and exceptions.
Complete sorting or dry lay, final checks, case numbers, labels and packing photographs.
Confirm loading, documents, destination, unloading conditions and estimated arrival milestone.
Changing sizes, quantities, holes or slots after scheduling affects material use, processing and inspection.
Multiple sizes, small batches, custom pieces and trial fitting increase process changes and identification work.
Production lacks a stable acceptance baseline until colour and finish samples are approved.
Replenishment or a new batch may require colour selection, a new sample or dry-lay adjustment.
Third-party inspection, witness points and corrective work require scheduled time.
Crate rules, weight limits, booking, trucks, ports and unloading conditions affect dispatch.
These figures help buyers understand base capability and ask scheduling questions. They do not mean capacity has been reserved for a specific order.
Machine counts and annual capacity indicate baseline fabrication capability but cannot determine one project date. Actual timing remains subject to material, drawing changes, size mix, current work, inspection and rework, packing, transport and external events.
Continue with factory capacity, the factory audit checklist and the quality inspection guide.
LEAD TIME FAQ
No. Lead time depends on granite and batch, drawing completeness, size mix, quantity, finish, quality requirements, current production, packing and destination. A written schedule should be prepared for the specific enquiry.
Ask the factory to connect the date to material status, relevant machinery, current work in progress, sample approval, production, inspection, packing and dispatch milestones, with responsibilities and prerequisites for each stage.
The order should define the starting condition, such as contract effectiveness, deposit, technical freeze, sample approval or material confirmation. Different starting conditions produce different dates; “after order” alone is ambiguous.
Yes, subject to agreement. Build the plan around installation sequence, sizes, case numbers, quantity per batch and site demand, then confirm inspection, packing, transport and replenishment for each release.
No. Factory completion, loading, vessel shipment and project arrival are separate milestones. Procurement documents should state which milestone is committed and treat transport and customs uncertainty separately.
Provide drawings, granite, sizes, quantity, finish, packing, destination and required date.